On March 25, 2016, the U.S. Department of Energy (DOE) announced that it would partner with Clean Line Energy Partners (Clean Line) to support the development of the Plains & Eastern 700-mile HVDC transmission line. Once completed, the transmission line will transport up to 4,000 MWs of wind power from the Oklahoma Panhandle to the Southeast. Clean Line’s partnership with the DOE revived the project, which was blocked in 2011 by Arkansas regulators.
Plains & Eastern HVDC Transmission Project Map
Key Details:
Implications
This case has important implications for transmission siting, given that it is the first test of the DOE’s backstop siting over the objections of a state regulator.
More Information
SNL: https://www.snl.com/InteractiveX/article.aspx?CDID=A-35883731-11819&KPLT=4
Clean Line: http://www.plainsandeasterncleanline.com/site/page/project-description
This report is part of the Grid Edge Minute series. To view all featured Minutes, please click here.
Contributing Author: Mark Ladisch